Casting a suspended slab means building strong formwork on well-braced props, fixing the steel exactly as the structural drawings show with spacers for cover, placing all pipes and conduits before the pour, then pouring structural concrete (usually C25) in one continuous operation, compacting it with a poker vibrator and curing it for at least 7 days. Props stay under the slab for at least 14 days in most cases. A typical house slab is 125 to 175 mm thick. The steps are simple, but each one must be checked before the next, because once the concrete is in, mistakes cannot be seen or easily fixed.
What do I need before casting a slab?
- Approved structural drawings showing slab thickness, steel sizes and spacing, beams and openings.
- Formwork and props for the whole area. See formwork and shuttering.
- Steel and binding wire per the bar bending schedule.
- Spacers (concrete blocks or plastic chairs) for bottom cover and chairs for top steel.
- Materials for the full pour, plus 10 percent extra. See concrete quantities.
- Mixers, vibrator, labour and water, or ready-mix trucks and a pump.
- Curing materials: water, plastic sheets or sacks.
Step 1: Build and check the formwork
Props on firm bases, braced both ways, with joists and boards tight and level. Check the soffit level and the edges before steel goes in. Openings for stairs and ducts must be boxed out.
Step 2: Fix the steel
- Lay bottom bars in the short direction first (unless the drawings say otherwise), then bars in the long direction.
- Tie intersections with binding wire.
- Place spacers so bottom cover is usually 20 to 25 mm.
- Fix top steel over beams and supports on chairs, at the height shown.
- Add extra bars around openings and at corners as the drawings require.
- Make sure beam steel is fully tied into column steel.

Step 3: Place services
Electrical conduits, junction boxes, plumbing sleeves and drain points go in now. Keep conduits between the top and bottom steel layers, never on the formwork below the bottom bars, and avoid bunching many conduits in one place. Mark where pipes will pass through.
Step 4: Inspect before the pour
The site engineer or clerk of works should check:
- formwork levels and props,
- steel sizes, spacing, laps and cover,
- services and openings,
- materials and equipment ready for a continuous pour.
Take photos of the steel before it is covered. See site supervision.
Step 5: Pour the concrete in one go
- Start early in the day to avoid the midday heat.
- Wet the formwork lightly.
- Pour from one end, working steadily so new concrete always meets fresh concrete.
- Compact with a poker vibrator: insert, hold until bubbles stop, withdraw slowly. Do not use it to move concrete sideways.
- Level with a straight edge to the right thickness, checked with marked pegs.
- Finish with a float or as the floor design requires.
- Take a slump test and cube samples.
If the pour must stop, form the joint where the engineer says, usually near the middle third of a span, never at a support.
Step 6: Cure and protect
Start curing as soon as the surface can take it: ponding water, wet sacks or plastic sheets. Keep it wet for at least 7 days. Keep loads off the slab: no stacking blocks on young concrete. See curing concrete in hot weather.
Step 7: Remove formwork and props
Slab boards can often come off after about 7 days with props left in, and props after 14 days or more, as the engineer instructs. Long spans, cantilevers and cold weather need longer. Do not remove props to reuse them while the slab above them is still young.
Ready-mix or site-mixed concrete for a slab?
| Site-mixed | Ready-mix with pump | |
|---|---|---|
| Consistency | Depends on batching discipline | Plant-controlled |
| Speed | Slower, many workers | Fast, fewer workers |
| Cost | Lower material price, more labour | Higher price per m³, less labour |
| Access | Works on tight sites | Needs road access for trucks and pump |
| Best for | Small slabs, remote areas | Larger slabs, urban sites |
For slabs above about 15 to 20 m³, ready-mix often gives better and faster results, and the price difference narrows once you count labour and mixer hire. See how to start a concrete business.
What are the common slab defects and their causes?
- Sagging in the middle: props removed too early or too few props.
- Cracks along beams or over supports: missing top steel or poor curing.
- Honeycombing on the underside: poor compaction or leaking formwork.
- Rust stains under the slab: steel too close to the surface.
- Uneven surface: no level pegs or poor screeding.
Most of these can be prevented by checks before the pour and patience after it.
Frequently asked questions
How thick should a house slab be?
Often 125 to 175 mm, depending on spans and loads. The engineer decides.
What concrete grade is used for slabs?
Usually C25 (about 1:1.5:3) or higher.
Can a slab be cast in two days?
It is better in one continuous pour. If a joint is unavoidable, place it where the engineer specifies.
When can I build walls on a new slab?
Light work after about 7 days. Heavy loads and the next floor after the engineer approves, often 14 days or more.
How long does a slab take to reach full strength?
Concrete reaches most of its design strength at 28 days, if it is cured properly.
Should a slab be cast in the rain?
Avoid it. Heavy rain washes out cement and spoils the surface. If rain starts, cover the fresh concrete with plastic sheets.