Formwork, also called shuttering, is the temporary mould that holds wet concrete in shape until it is strong enough to stand on its own. In Tanzania most house builders use timber boards or plywood held up by timber or steel props, while bigger contractors use steel or aluminium systems they can reuse many times. Good formwork is strong, tight and level: it must carry the full weight of wet concrete and workers without moving, stop the cement paste leaking out, and leave a clean surface. As a rough guide, side forms to columns and beams can come off after 1 to 2 days, slab soffit boards after about 7 days with props left underneath, and the props under slabs after 14 days or more. Your engineer has the final say.
What is formwork in construction?
Formwork is everything that shapes and supports concrete while it hardens:
- Sheathing: the boards or plywood the concrete touches.
- Supports: joists, bearers and props (often called "props" or "nguzo za muda") that carry the load down to the ground.
- Ties and bracing: wires, bolts, clamps and diagonal braces that stop the forms spreading or leaning.
Wet concrete weighs about 2,400 kg per cubic metre. A 150 mm slab over a 4 by 4 metre room weighs around 5.8 tonnes before anyone stands on it. That is why weak props, rotten boards and missing braces cause collapses.
Which type of formwork should I use?
| Type | Best for | Reuses | Notes |
|---|---|---|---|
| Timber boards | Small houses, footings, beams | 3 to 6 | Cheap and easy to cut, but leaks and warps if not oiled and tight |
| Plywood (marine or film-faced) | Slabs and smooth faces | 10 to 30 | Smoother finish, fewer joints, costs more up front |
| Steel panels | Columns, walls, repeated work | 50 or more | Strong and accurate, heavy, needs crane or many hands |
| Aluminium systems | Large apartment and commercial jobs | 100 or more | Fast and light, expensive, rented or bought by big contractors |
| Steel props and timber or steel beams | Supporting slabs | Many years | Adjustable height, safer than loose timber poles |
For a typical family house, plywood on timber joists with adjustable steel props is a good balance of cost and quality. Eucalyptus poles (mikaratusi) are still common as props, but they must be straight, sound and braced, and they need hardwood wedges or base plates so they do not sink into soft ground.
How do I build formwork that does not fail?
- Start from a firm base. Props on soft soil or loose fill sink when the concrete goes in. Put them on boards or base plates on compacted ground.
- Space the supports correctly. For a 150 mm slab, props are typically 0.9 to 1.2 m apart each way under joists. Follow the engineer's or supplier's spacing.
- Brace in both directions. Tall props need diagonal bracing so the whole system cannot sway.
- Make it tight. Close the gaps between boards, tape or seal joints, and fix the corners well. Leaking paste leaves honeycombed, weak concrete.
- Check line and level. Use a level or laser before pouring. A slab that sags in the middle stays that way.
- Oil the faces. Release agent or used-oil substitutes stop concrete sticking and make stripping easier. Keep oil off the steel.
- Fit the cover spacers. Steel must sit on spacers so concrete covers it fully. See steel reinforcement bars.

How long should formwork stay before removal?
Concrete gains strength over days, and how fast depends on cement type, temperature and curing. A common guide for ordinary Portland cement in warm Tanzanian conditions:
| Element | Minimum time before striking |
|---|---|
| Column and wall sides | 1 to 2 days |
| Beam sides | 1 to 2 days |
| Slab soffit boards, props left in place | About 7 days |
| Props under slabs | 14 days or more |
| Props under beams | 14 to 21 days |
| Cantilevers and long spans | As the engineer specifies, often longer |
Cold weather, wet weather, slower cements like 32.5 grade and heavy loads from the floor above all mean leaving props longer. Never let a crew load bricks, steel or another slab onto fresh concrete that is still young. Cube test results tell you whether the concrete has reached the strength needed.
How much does formwork cost?
Formwork is a large share of the cost of a concrete frame, often 25 to 40 percent of the cost of the concrete elements themselves, because of materials and labour. Ways to keep it down:
- Repeat the same column and beam sizes so forms can be reused.
- Use plywood and steel props you can reuse on several jobs, or rent them.
- Clean and oil forms after each use, and store them flat and dry.
- Plan pours so each set of forms is used again quickly.
See how to reduce construction costs without losing quality.
What are the most common formwork mistakes?
- Props standing on loose soil or broken blocks.
- No bracing on tall props.
- Gaps between boards that leak cement paste.
- Forms not checked for level before the pour.
- Stripping too early, especially under slabs and beams.
- Reusing split or warped boards that bulge under load.
Frequently asked questions
What is the difference between formwork and shuttering?
They mean the same thing. In Tanzania "shuttering" is often used for the boards and "formwork" for the whole system, including props.
Can I remove slab props after 7 days?
Usually not all of them. The boards can often come off after about 7 days if props are left or re-propped under the slab. Full prop removal is normally 14 days or more. Ask your engineer.
Is plywood better than timber boards?
For slabs and visible faces, yes. It gives a smoother finish, fewer joints and more reuses. Timber boards are fine for footings and hidden work.
Do I need an engineer to check formwork?
For slabs, beams and anything above one storey, yes. A site engineer should check props, spacing and bracing before every pour. See site supervision.