Opening hoursMon to Sat, 8am to 5pm
Head officeDar es Salaam, Tanzania

How to Calculate Cement, Sand and Aggregate for Concrete (With Worked Examples)

How many bags of cement does a slab need? A simple method to calculate cement, sand and kokoto for any concrete job, with tables and worked examples.

Workers loading sand, aggregate and water into gauge boxes beside a mixer on a site in Kenya.
Kenya Photo: Mugambi Muriuki / Wikimedia Commons, CC BY-SA 4.0
Share

To calculate concrete materials, work out the volume of concrete in cubic metres, then use the mix ratio to split it into cement, sand and aggregate. For one cubic metre of 1:2:4 concrete (about C20) you need roughly 6.5 to 7 bags of 50 kg cement, 0.45 m³ of sand and 0.9 m³ of aggregate (kokoto). For 1:1.5:3 (about C25), used for columns, beams and slabs, you need about 8 to 8.5 bags, 0.42 m³ of sand and 0.84 m³ of aggregate. Add 5 to 10 percent for waste. The method below shows how to get these numbers and how to apply them to a slab, a column or a footing.

What is the formula for concrete materials?

Dry materials shrink in volume when water is added, because sand fills the gaps between stones and cement fills the gaps in sand. So the dry volume you need is about 1.54 times the wet volume of concrete.

  1. Wet volume = length × width × thickness (m³).
  2. Dry volume = wet volume × 1.54.
  3. Total parts in the ratio, for example 1 + 2 + 4 = 7.
  4. Cement volume = dry volume × 1 ÷ 7. Multiply by 1,440 kg/m³ to get kg, then divide by 50 for bags.
  5. Sand = dry volume × 2 ÷ 7.
  6. Aggregate = dry volume × 4 ÷ 7.

For 1 m³ of 1:2:4: dry volume 1.54 m³, cement = 1.54 ÷ 7 = 0.22 m³ = 317 kg = about 6.3 bags (round up to 6.5 to 7 to allow for losses).

How much cement, sand and aggregate per cubic metre?

Mix ratioApprox. gradeCement (50 kg bags)Sand (m³)Aggregate (m³)Typical use
1:3:6C104.40.661.32Blinding, mass fill
1:2:4C206.3 to 70.440.88Footings, ground slabs
1:1.5:3C258 to 8.50.420.84Columns, beams, suspended slabs
1:1:2C30110.390.77High-strength work (engineer's design)

Figures are for 1 m³ of finished concrete, before waste. For important structural work, an engineer may specify a designed mix by weight instead.

Heaps of aggregate and sand with cement bags and workers carrying buckets on a site in Kenya.
Count bags, sand and kokoto before the pour so the job does not stop halfway. Kenya Photo: Mugambi Muriuki / Wikimedia Commons, CC BY-SA 4.0

Worked example: how many bags of cement for a slab?

A suspended slab for a room 5 m by 4 m, 150 mm thick, in 1:1.5:3:

  • Volume = 5 × 4 × 0.15 = 3.0 m³.
  • Cement = 3.0 × 8.5 = about 25.5 bags.
  • Sand = 3.0 × 0.42 = 1.26 m³.
  • Aggregate = 3.0 × 0.84 = 2.52 m³.
  • Add 10 percent for waste: about 28 bags, 1.4 m³ sand, 2.8 m³ aggregate.

A typical 7 m³ tipper load of sand or aggregate covers much more than this, so plan deliveries to match the whole job.

Worked example: columns and footings

Ten columns of 230 by 230 mm, each 3 m high, in 1:1.5:3:

  • Volume = 10 × 0.23 × 0.23 × 3 = 1.59 m³.
  • Cement = 1.59 × 8.5 = about 13.5 bags, plus waste = 15 bags.

Strip footing 600 mm wide, 200 mm deep, 40 m long, in 1:2:4:

  • Volume = 0.6 × 0.2 × 40 = 4.8 m³.
  • Cement = 4.8 × 7 = about 34 bags.
  • Sand = 4.8 × 0.44 = 2.1 m³; aggregate = 4.8 × 0.88 = 4.2 m³.

Don't forget the blinding under footings (usually 50 mm of 1:3:6).

How do I convert to tipper loads and wheelbarrows?

UnitApprox. volume
50 kg bag of cement0.035 m³
Standard wheelbarrow, level0.06 to 0.07 m³
Small tipper (lori la tani 7)about 5 to 7 m³
Large tipper10 to 15 m³ or more

Ask the supplier how many cubic metres a load holds, and check it on arrival. A load measured by "trip" can vary a lot. See building materials prices.

What about the steel and water?

  • Water: about 25 to 30 litres per bag of cement, adjusted on site.
  • Steel: taken from the structural drawings or a bar bending schedule, not from the concrete volume.
  • Formwork: calculated from surface area. See formwork and shuttering.

How do I estimate concrete for a whole house?

For budgeting, break the structure into parts and add them up:

ElementHow to measureTypical mix
BlindingFooting area × 0.05 m1:3:6
Strip footingsWidth × depth × total length1:2:4
Ground beamsWidth × depth × length1:1.5:3
Ground slabArea × thickness (often 0.1 to 0.15 m)1:2:4
ColumnsWidth × depth × height × number1:1.5:3
Lintels and ring beamWidth × depth × total length1:1.5:3
Suspended slabArea × thickness1:1.5:3

Work out each volume, multiply by the cement, sand and aggregate figures for its mix, then add them up. For a simple 120 m² single-storey house, the concrete is often in the range of 25 to 40 m³ depending on foundations and slab, which is roughly 180 to 280 bags of cement for concrete alone, before blockwork and plaster.

What causes concrete estimates to go wrong?

  • Forgetting blinding, ground beams or stair slabs.
  • Using site trips instead of measured cubic metres.
  • Ignoring uneven excavations, which take more concrete than the drawing shows.
  • Cement lost to rain or theft on site. See how to stop theft of materials.
  • Over-watering, which leads to more cement being added later.

Frequently asked questions

How many bags of cement are in 1 cubic metre of concrete?

About 6.5 to 7 bags for 1:2:4 and 8 to 8.5 bags for 1:1.5:3.

Why multiply by 1.54?

Because dry sand, aggregate and cement take up more space than the finished concrete. 1.54 is a standard allowance for that shrinkage and some waste.

Is 32.5 or 42.5 cement better for slabs?

42.5 is usually preferred for structural concrete because it gains strength faster. See cement types.

How do I calculate concrete for a round column?

Volume = 3.14 × radius × radius × height. Then apply the same per-m³ figures.

Want an accurate bill of quantities?

Vika Construction prepares detailed estimates and BOQs. Contact us to price your project. See also bill of quantities explained.

Found this useful? Share it with someone who is building.

Planning a building project?

Tell us where the site is and what you want built.