To calculate concrete materials, work out the volume of concrete in cubic metres, then use the mix ratio to split it into cement, sand and aggregate. For one cubic metre of 1:2:4 concrete (about C20) you need roughly 6.5 to 7 bags of 50 kg cement, 0.45 m³ of sand and 0.9 m³ of aggregate (kokoto). For 1:1.5:3 (about C25), used for columns, beams and slabs, you need about 8 to 8.5 bags, 0.42 m³ of sand and 0.84 m³ of aggregate. Add 5 to 10 percent for waste. The method below shows how to get these numbers and how to apply them to a slab, a column or a footing.
What is the formula for concrete materials?
Dry materials shrink in volume when water is added, because sand fills the gaps between stones and cement fills the gaps in sand. So the dry volume you need is about 1.54 times the wet volume of concrete.
- Wet volume = length × width × thickness (m³).
- Dry volume = wet volume × 1.54.
- Total parts in the ratio, for example 1 + 2 + 4 = 7.
- Cement volume = dry volume × 1 ÷ 7. Multiply by 1,440 kg/m³ to get kg, then divide by 50 for bags.
- Sand = dry volume × 2 ÷ 7.
- Aggregate = dry volume × 4 ÷ 7.
For 1 m³ of 1:2:4: dry volume 1.54 m³, cement = 1.54 ÷ 7 = 0.22 m³ = 317 kg = about 6.3 bags (round up to 6.5 to 7 to allow for losses).
How much cement, sand and aggregate per cubic metre?
| Mix ratio | Approx. grade | Cement (50 kg bags) | Sand (m³) | Aggregate (m³) | Typical use |
|---|---|---|---|---|---|
| 1:3:6 | C10 | 4.4 | 0.66 | 1.32 | Blinding, mass fill |
| 1:2:4 | C20 | 6.3 to 7 | 0.44 | 0.88 | Footings, ground slabs |
| 1:1.5:3 | C25 | 8 to 8.5 | 0.42 | 0.84 | Columns, beams, suspended slabs |
| 1:1:2 | C30 | 11 | 0.39 | 0.77 | High-strength work (engineer's design) |
Figures are for 1 m³ of finished concrete, before waste. For important structural work, an engineer may specify a designed mix by weight instead.

Worked example: how many bags of cement for a slab?
A suspended slab for a room 5 m by 4 m, 150 mm thick, in 1:1.5:3:
- Volume = 5 × 4 × 0.15 = 3.0 m³.
- Cement = 3.0 × 8.5 = about 25.5 bags.
- Sand = 3.0 × 0.42 = 1.26 m³.
- Aggregate = 3.0 × 0.84 = 2.52 m³.
- Add 10 percent for waste: about 28 bags, 1.4 m³ sand, 2.8 m³ aggregate.
A typical 7 m³ tipper load of sand or aggregate covers much more than this, so plan deliveries to match the whole job.
Worked example: columns and footings
Ten columns of 230 by 230 mm, each 3 m high, in 1:1.5:3:
- Volume = 10 × 0.23 × 0.23 × 3 = 1.59 m³.
- Cement = 1.59 × 8.5 = about 13.5 bags, plus waste = 15 bags.
Strip footing 600 mm wide, 200 mm deep, 40 m long, in 1:2:4:
- Volume = 0.6 × 0.2 × 40 = 4.8 m³.
- Cement = 4.8 × 7 = about 34 bags.
- Sand = 4.8 × 0.44 = 2.1 m³; aggregate = 4.8 × 0.88 = 4.2 m³.
Don't forget the blinding under footings (usually 50 mm of 1:3:6).
How do I convert to tipper loads and wheelbarrows?
| Unit | Approx. volume |
|---|---|
| 50 kg bag of cement | 0.035 m³ |
| Standard wheelbarrow, level | 0.06 to 0.07 m³ |
| Small tipper (lori la tani 7) | about 5 to 7 m³ |
| Large tipper | 10 to 15 m³ or more |
Ask the supplier how many cubic metres a load holds, and check it on arrival. A load measured by "trip" can vary a lot. See building materials prices.
What about the steel and water?
- Water: about 25 to 30 litres per bag of cement, adjusted on site.
- Steel: taken from the structural drawings or a bar bending schedule, not from the concrete volume.
- Formwork: calculated from surface area. See formwork and shuttering.
How do I estimate concrete for a whole house?
For budgeting, break the structure into parts and add them up:
| Element | How to measure | Typical mix |
|---|---|---|
| Blinding | Footing area × 0.05 m | 1:3:6 |
| Strip footings | Width × depth × total length | 1:2:4 |
| Ground beams | Width × depth × length | 1:1.5:3 |
| Ground slab | Area × thickness (often 0.1 to 0.15 m) | 1:2:4 |
| Columns | Width × depth × height × number | 1:1.5:3 |
| Lintels and ring beam | Width × depth × total length | 1:1.5:3 |
| Suspended slab | Area × thickness | 1:1.5:3 |
Work out each volume, multiply by the cement, sand and aggregate figures for its mix, then add them up. For a simple 120 m² single-storey house, the concrete is often in the range of 25 to 40 m³ depending on foundations and slab, which is roughly 180 to 280 bags of cement for concrete alone, before blockwork and plaster.
What causes concrete estimates to go wrong?
- Forgetting blinding, ground beams or stair slabs.
- Using site trips instead of measured cubic metres.
- Ignoring uneven excavations, which take more concrete than the drawing shows.
- Cement lost to rain or theft on site. See how to stop theft of materials.
- Over-watering, which leads to more cement being added later.
Frequently asked questions
How many bags of cement are in 1 cubic metre of concrete?
About 6.5 to 7 bags for 1:2:4 and 8 to 8.5 bags for 1:1.5:3.
Why multiply by 1.54?
Because dry sand, aggregate and cement take up more space than the finished concrete. 1.54 is a standard allowance for that shrinkage and some waste.
Is 32.5 or 42.5 cement better for slabs?
42.5 is usually preferred for structural concrete because it gains strength faster. See cement types.
How do I calculate concrete for a round column?
Volume = 3.14 × radius × radius × height. Then apply the same per-m³ figures.