A bar bending schedule (BBS) is a table prepared from the structural drawings that lists every steel bar in a part of the building: its mark, diameter, shape, cutting length, number and total weight. Steel fixers use it to cut and bend bars, and the client or quantity surveyor uses it to order steel and check quantities. To use a BBS, you read each row to see how many bars of what size and length are needed, add up the total length per diameter, convert it to weight using about diameter² ÷ 162 kg per metre, and divide by 12 metres to estimate the number of standard bars to buy, allowing for laps and offcuts.
What does a bar bending schedule look like?
| Member | Bar mark | Type and size | No. of members | No. of bars each | Total no. | Cutting length (m) | Total length (m) | Shape |
|---|---|---|---|---|---|---|---|---|
| Column C1 | 01 | Y12 | 10 | 4 | 40 | 3.60 | 144.0 | Straight with bend at base |
| Column C1 | 02 | Y8 | 10 | 20 | 200 | 0.90 | 180.0 | Rectangular link |
| Beam B1 | 03 | Y12 | 4 | 4 | 16 | 5.40 | 86.4 | Straight with hooks |
| Beam B1 | 04 | Y8 | 4 | 28 | 112 | 1.10 | 123.2 | Rectangular link |
Each row tells the fixer what to make. The shape column often uses standard shape codes with a small sketch and dimensions.
How is cutting length calculated?
Cutting length is the straight length of bar before bending. It includes:
- the clear length of the bar in the member,
- hooks or bends at the ends,
- laps where bars join,
- minus small deductions for bends (bends make the bar slightly longer around the outside).
Example: a rectangular link for a 230 by 230 mm column with 25 mm cover.
- Inner size of link = 230 − 2 × 25 = 180 mm each side.
- Perimeter = 4 × 180 = 720 mm.
- Add two hooks of about 75 to 100 mm each.
- Cutting length is roughly 0.90 m.
Engineers use standard formulas, but on site the rule is: cut a test bar, bend it, check it fits the cage, then cut the rest.

How do I convert a BBS into steel weight?
Use the weight per metre:
| Bar | kg per m |
|---|---|
| Y8 | 0.395 |
| Y10 | 0.617 |
| Y12 | 0.888 |
| Y16 | 1.58 |
| Y20 | 2.47 |
From the example table:
- Y12: 144.0 + 86.4 = 230.4 m × 0.888 = 204.6 kg.
- Y8: 180.0 + 123.2 = 303.2 m × 0.395 = 119.8 kg.
How many 12 metre bars do I order?
Divide the total length by 12 m, then add for laps and offcuts:
- Y12: 230.4 ÷ 12 = 19.2, round up and add about 5 to 10 percent = about 21 bars.
- Y8: 303.2 ÷ 12 = 25.3, add waste = about 27 to 28 bars.
Plan cutting so offcuts from long bars can be used for short pieces like links and L-bars. This "cutting plan" can save several percent of steel on a house. See steel reinforcement bars.
What are lap lengths and why do they matter?
When a bar is not long enough, two bars are overlapped and tied. The lap must be long enough to transfer the force, often around 40 to 50 times the bar diameter, so about 480 to 600 mm for Y12. The engineer specifies laps on the drawings. Laps should be staggered, not all in the same section of a beam or column.
Who prepares the bar bending schedule?
Usually the structural engineer, the contractor's site engineer or a quantity surveyor, from the approved structural drawings. Do not let anyone guess steel quantities from experience on a structural job. The BBS should match the drawings exactly. See how to read house drawings.
How do I check steel on site against the schedule?
- Count the bars in each element and compare with the schedule.
- Measure link spacing with a tape, especially near column and beam ends.
- Check bar sizes by reading the markings rolled on the bar or measuring with a caliper.
- Check laps: length, position and staggering.
- Check cover: spacers in place on all faces.
- Check bends: correct shapes, no cracked bends, hooks closed to the right angle.
Record what you checked with photos before concrete is poured. See site supervision and quality control.
On larger jobs, keep the bar bending schedule on site in a plastic folder next to the drawings. Steel fixers, the site engineer and the client's supervisor can all refer to it, and any changes approved by the engineer can be marked on the same copy.
Frequently asked questions
What is the purpose of a bar bending schedule?
To list exactly what steel to cut and bend, and to calculate quantities for ordering and payment.
How do I calculate steel weight?
Weight per metre is about diameter² ÷ 162. Multiply by total length.
How long is a standard steel bar in Tanzania?
Usually 12 metres.
What is a shape code?
A standard code that describes how a bar is bent, used with dimensions on the schedule.
What is cover in reinforced concrete?
The thickness of concrete between the steel and the surface, usually 20 to 50 mm depending on the element and exposure. It protects steel from rust and fire.
Why are links bent with 135 degree hooks?
Hooks bent to 135 degrees anchor into the concrete core and stay closed when the column is stressed, which matters most in earthquake areas.
Can I use a different bar size from the schedule?
Not without the engineer's approval. Changing sizes changes strength.
Is a bar bending schedule needed for a small house?
It is very useful. Even for a single-storey house, a simple schedule prevents overbuying steel and helps check that columns, beams and the ring beam get the right bars.