A gravel road in Tanzania is built by clearing and shaping the road formation, building a compacted subgrade, then laying 150 to 200 mm of good-quality natural gravel, compacted at the right moisture, with a camber of about 4 to 6% so rain runs off into side drains and mitre drains. Culverts carry water under the road at low points. A new gravel road usually costs about TSh 60 to 200 million per km in 2026, depending on width, soil, haul distance and drainage structures. Gravel roads are cheap to build but need grading several times a year and regravelling every 4 to 7 years.
Most of the roads in Tanzania's district network are gravel or earth. They connect farms, villages, schools, mines and estates. A well-built gravel road can carry trucks through the rainy season. A badly built one turns to mud in the first storm.
When is a gravel road the right choice?
Gravel makes sense when:
- traffic is low, usually below about 200 to 300 vehicles a day
- the budget for sealing is not available yet
- the road is temporary or the first stage of a road that will be sealed later
- good gravel is available close to the site
- the road serves farms, plantations, quarries, mines or new estates
Once traffic grows, the cost of grading and regravelling plus the dust and vehicle wear usually make a sealed road cheaper over its life. Our road surface comparison explains the options.
What makes good road gravel?
The wearing course gravel is the most important material on the job. It must be strong enough to carry traffic, have enough fine material to bind together when dry, but not so much clay that it turns slippery and soft when wet.
Engineers test gravel for:
- Grading: a good mix of stone, sand and fines.
- Plasticity index (PI): a measure of clay content. Wearing course gravel usually needs a moderate PI, enough to bind but not so much that it becomes slippery.
- CBR (California Bearing Ratio): a measure of strength when soaked.
- Maximum stone size: usually below about 37.5 mm, so the road is not too rough.
Common sources in Tanzania include lateritic gravel (red murram), weathered rock and quartzitic gravels. Quality varies a lot even within one borrow pit, so test samples from across the pit, not just one spot.

How is a gravel road built, step by step?
1. Survey and design
The alignment, levels and drainage are surveyed and designed. Even a simple estate road benefits from a drawing showing the centreline, the camber, the drains and where culverts go. See our guide to site surveys.
2. Clearing and grubbing
Trees, roots, bush and topsoil are removed across the full road reserve width. Topsoil holds organic matter that rots and settles, so it is stockpiled for later use on slopes.
3. Earthworks and formation
The road is cut and filled to the design levels. On flat ground, the road is raised above the surrounding land so it drains. Soft spots are dug out and replaced with better material. Fills are placed in layers and compacted.
4. Subgrade preparation
The top of the formation is shaped to camber and compacted. This is the foundation of the road. If it is weak, the gravel on top will fail regardless of quality.
5. Drainage
Side drains are cut along both edges. Mitre drains (turnouts) take water from the side drains away from the road at regular intervals before it gathers enough to erode. Culverts are placed at low points and stream crossings. On slopes, scour checks (small barriers in the drain) slow the water.
6. Placing the gravel wearing course
Gravel is hauled, tipped at measured spacing, spread by grader, watered to the right moisture and mixed. The usual compacted thickness is 150 to 200 mm, sometimes in two layers.
7. Compaction
The layer is rolled with a vibratory roller, then finished with a smooth drum or pneumatic roller. Density tests confirm it meets the target. See road compaction explained.
8. Finishing
The final camber is checked, shoulders formed, signs placed and drains cleaned.
What width and camber should a gravel road have?
| Road | Typical carriageway width | Camber |
|---|---|---|
| Farm or estate track | 4 to 5 m | 4 to 6% |
| District or feeder road | 5.5 to 6.5 m | 4 to 6% |
| Busier gravel road with trucks | 6.5 to 7.5 m | 4 to 6% |
A gravel road needs more camber than a sealed road because water soaks into the surface. Too little camber and water ponds in the middle. Too much and vehicles slide and the edges erode.

How much does a gravel road cost in Tanzania?
| Item | Share of cost |
|---|---|
| Clearing and earthworks | 20 to 30% |
| Gravel wearing course (supply, haul, place, compact) | 35 to 50% |
| Drainage and culverts | 15 to 30% |
| Preliminaries, survey, testing | 10 to 15% |
Rough 2026 planning ranges:
- New gravel road with drainage: TSh 60 to 200 million per km (about USD 23,000 to 77,000).
- Regravelling: TSh 25 to 70 million per km.
- Spot improvement of bad sections: priced per site.
- Routine grading: a small fraction of the build cost each year.
The biggest swing is haul distance. Every extra 10 km of haul adds noticeably to the cost of each cubic metre of gravel. One kilometre of road 6 m wide with 150 mm of gravel needs roughly 1,000 m³ of compacted gravel, more once you allow for shoulders and losses. See the full road construction cost guide for sealed roads.
How do you maintain a gravel road?
- Routine grading: two to four times a year to restore camber and fill ruts.
- Drain cleaning: before and after the rainy season.
- Spot regravelling: fill soft or worn spots.
- Regravelling: replace the wearing course every 4 to 7 years, as traffic and rain carry gravel away. Roads lose roughly 10 to 25 mm a year depending on traffic and rainfall.
- Culvert clearing: remove silt and debris so water passes.
- Vegetation control: cut grass so it does not block drains or sight lines.
Grading a road that is too dry produces dust and loose gravel. Grading just after rain, when the surface is damp, gives a better result.
Can a gravel road be upgraded to tarmac later?
Yes, and building in stages is common in Tanzania. Many district roads start as gravel and are sealed years later when traffic and budgets grow. If you think a road might be sealed in future, a few choices now save money later:
- Get the alignment and levels right. Sharp bends, steep grades and low sections that flood are expensive to change once houses and fences line the road.
- Reserve enough width. A sealed road with shoulders and drains needs more space than a narrow gravel track.
- Build the drainage to the final standard. Culverts sized for the future road do not need replacing.
- Use good material in the lower layers. A sound gravel layer can often be reworked into the sub-base of the sealed road.
- Keep records. Layer thicknesses and test results help the designer of the later upgrade.
When the upgrade comes, the existing gravel is usually reshaped, topped up or stabilised, a new base is added, and a surface dressing or asphalt goes on top. Our article on road construction layers shows what the finished structure looks like.
Common mistakes with gravel roads
- Using clayey soil instead of tested gravel.
- No camber, so water sits on the road.
- No mitre drains, so side drains overflow and erode.
- Culverts too small or laid too high, flooding the road upstream.
- Gravel dumped and spread with no water or rolling.
- Building the road at the same level as the land, so it becomes a channel in the rain.
Frequently asked questions
How thick should the gravel layer be?
Usually 150 to 200 mm after compaction for the wearing course. Heavier traffic and weaker subgrades need thicker layers or a separate gravel base.
How long does a gravel road last?
The road formation can last decades, but the gravel surface wears away and needs replacing every 4 to 7 years, with grading several times a year in between.
Can I build a gravel road to my farm or estate?
Yes. Get a simple design with levels and drainage, test the gravel, and compact properly. If it joins a public road, ask the road authority about the junction.
What is murram?
Murram is a common East African name for lateritic gravel, a red or brown natural gravel used widely for road surfaces and fills. Quality varies, so it should be tested.
Is gravel cheaper than paving blocks for an estate road?
To build, yes, by a big margin. Over 15 years, with grading, regravelling and dust, paving or sealing may come out closer than people expect on busy estate roads. See driveways and access roads.