The Tanzanite Bridge, also called the New Selander Bridge, is a cable-stayed sea bridge in Dar es Salaam that runs just offshore from the Msasani side towards Ocean Road and the city centre. It was built to relieve the old two-lane Selander Bridge, which was one of the worst traffic bottlenecks in the city. South Korea's GS Engineering and Construction built it, with Yooshin Engineering and Afrisa Consulting as consultants, and it opened to traffic on 1 February 2022. The cost was roughly US$120 million (about TSh 244 billion), funded by the Tanzanian government with financing support from South Korea. The bridge crossing over the water is about 1 km long, with approach roads making up a longer project, and unlike the Nyerere Bridge in Kigamboni, it is toll-free.
Why was the Tanzanite Bridge built?
Almost all traffic between the city centre and the Masaki, Oyster Bay and Msasani areas used to squeeze onto Ali Hassan Mwinyi Road and the old Selander Bridge over the Msimbazi creek mouth. The old bridge had two lanes and no room to widen. Morning and evening jams often stretched for kilometres.
Building another bridge beside it on land would have meant demolishing homes and offices. The engineers chose to take the new road out over the sea along the coast instead. That gave a new route without large demolitions, and a striking landmark on the waterfront.
| Fact | Detail |
|---|---|
| Names | Tanzanite Bridge, New Selander Bridge |
| Type | Cable-stayed sea bridge with approach roads |
| Over-water length | About 1 km |
| Contractor | GS Engineering and Construction (South Korea) |
| Consultants | Yooshin Engineering, Afrisa Consulting |
| Opened to traffic | 1 February 2022 |
| Cost | About US$120 million (TSh 244 billion) |
| Toll | None |
How do you build a bridge over the sea?
Building in the sea brings problems you never meet on land: waves, tides, salt and soft seabed. The main steps are:
- Temporary access. Contractors build a temporary jetty or use barges so machines can reach each pier.
- Piled foundations. Steel casings are driven or drilled into the seabed, then filled with reinforced concrete to form deep piles down to firm ground.
- Pile caps and piers. Concrete caps tie the piles together, and piers rise from them.
- Towers and cables. The main span uses concrete towers with fans of steel cables holding the deck.
- Deck. Precast or cast-in-place segments form the road deck between the piers and from the towers.
Salt is the long-term enemy. Concrete in the splash zone must be dense, with thick cover over the steel and sometimes protective coatings. The same rules apply on a smaller scale to houses near the coast. See building near the coast and concrete grades.

What has the bridge changed?
The bridge has cut travel times between the city centre and the northern peninsula, especially at rush hour, and taken pressure off the old Selander Bridge. It also added a new public waterfront. On weekends many people walk or drive across to see the city skyline from the sea.
For property, the effects are smaller than with the Kigamboni bridge, because Masaki and Oyster Bay were already the most expensive parts of Dar es Salaam. The main gain is easier access between offices in the centre and homes on the peninsula. New apartment buildings have gone up near the Kivukoni end, close to the bridge approaches.
How is the Tanzanite Bridge different from the Nyerere Bridge?
Both are cable-stayed bridges in Dar es Salaam, but they serve different jobs. The Nyerere Bridge crosses the Kurasini creek to open up Kigamboni and is paid for by tolls. The Tanzanite Bridge runs along the coast to relieve an existing route and is free to use. Read our guide to the Nyerere Bridge.

What does it mean for traffic planning in Dar es Salaam?
The bridge is one part of a larger effort to fix Dar es Salaam's traffic, alongside the BRT bus lanes, the Mfugale and Ubungo flyovers and the SGR. Each project removes one bottleneck, and traffic often moves to the next one. That is why planners talk about networks, not single projects. See Dar es Salaam BRT phases and Ubungo Interchange and Mfugale Flyover.
How long did the Tanzanite Bridge take to build?
The contract was signed in 2018 after years of planning, and construction ran for about three years, through the COVID-19 period, before the bridge opened in early 2022. Work over the sea is slower than on land, because each pile and pier depends on tides, weather and marine equipment. Delays for weather are normal on marine projects, and a good programme includes time for them.
For anyone planning a building project, the same lesson applies on land: build realistic time into the programme for rain, deliveries and approvals. See how to build a realistic construction programme.
Frequently asked questions
Do you pay a toll on the Tanzanite Bridge?
No. The bridge is free to use.
When did the Tanzanite Bridge open?
It opened to traffic on 1 February 2022.
Who built the Tanzanite Bridge?
GS Engineering and Construction of South Korea, with Yooshin Engineering and Afrisa Consulting as consultants.
Is the old Selander Bridge still used?
Yes. It still carries local traffic, but with much less congestion.
Why is it called the Tanzanite Bridge?
It is named after tanzanite, the blue gemstone found only in Tanzania, near Mererani in the Manyara Region.
Can pedestrians and cyclists use the Tanzanite Bridge?
The bridge has walkways, and many people walk across it to enjoy the sea views, especially at weekends. Follow the signs and safety rules on site.