Opening hoursMon to Sat, 8am to 5pm
Head officeDar es Salaam, Tanzania

Nyerere Bridge (Kigamboni Bridge): How It Was Built and What It Did for Kigamboni

Before 2016, getting to Kigamboni meant a ferry queue. The 680 m Nyerere Bridge changed that and turned Kigamboni into one of Dar es Salaam's busiest building areas.

The Nyerere Bridge in Kigamboni, Dar es Salaam, with its tall white cable-stayed tower above a wide road.
Nyerere Bridge, Kigamboni Photo: Mzalendo2016 / Wikimedia Commons, CC BY-SA 4.0
Share

The Nyerere Bridge, still widely called the Kigamboni Bridge, is a 680 metre cable-stayed bridge across the Kurasini creek in Dar es Salaam. It links Kurasini on the city side with Kigamboni and opened to traffic in April 2016 after four years of construction. It was built by Chinese contractors China Railway Jiangchang Engineering and China Major Bridge Engineering, designed by Arab Consulting Engineers, and cost roughly US$136 million (about TSh 254 billion with the approach roads). The National Social Security Fund (NSSF) paid about 60 percent and the government about 40 percent, and the bridge recovers its cost through tolls. For people building in Kigamboni, it turned a ferry-dependent peninsula into a place you can drive to from the city in minutes.

Why did Dar es Salaam need the Kigamboni bridge?

Kigamboni sits just across the harbour mouth from the city centre, but for decades the only quick crossing was the ferry from Magogoni. Ferries were crowded, queues were long and breakdowns stranded people. The long road around through Kongowe and Mjimwema took hours in traffic. That held back Kigamboni, even though it had space, beaches and land much cheaper than Masaki or Mikocheni.

A fixed crossing was discussed for years. Work finally started in February 2012, and the bridge opened in April 2016. President Magufuli inaugurated it on 19 April 2016 and named it after Mwalimu Julius Nyerere.

FactDetail
NameNyerere Bridge (Kigamboni Bridge)
LengthAbout 680 m
TypeCable-stayed bridge
CrossesKurasini creek, between Kurasini and Kigamboni
BuiltFebruary 2012 to April 2016
ContractorsChina Railway Jiangchang Engineering and China Major Bridge Engineering
DesignerArab Consulting Engineers
CostAbout US$136 million (TSh 254 billion including approach roads)
FundingAbout 60 percent NSSF, 40 percent government
PaymentToll bridge

How is a cable-stayed bridge built?

A cable-stayed bridge carries its deck on straight cables that run directly from tall towers, called pylons, down to the deck. It suits medium spans like the Kurasini creek, where a ship channel or deep water makes many piers in the water impractical.

The work follows a clear order:

  1. Deep foundations. In a tidal creek with soft marine soils, the towers and piers sit on large bored piles drilled down to firm ground. Each pile is a steel cage filled with concrete.
  2. Pile caps and towers. A thick concrete cap ties the piles together. The towers rise from it in stages, cast with climbing formwork.
  3. Deck segments. The deck is built out from the towers in segments. Each new segment is supported by a new pair of cables before the next goes on, so the deck grows in balance on both sides.
  4. Cable tuning. Engineers adjust cable forces so the deck sits at the right level and shape.
  5. Approach roads, toll plaza and finishes. Roads, lighting, barriers and the toll gate at Vijibweni complete the job.
The Kigamboni bridge deck under construction over the creek, with cranes on top of its two towers.
The bridge during construction. The deck grows out from each tower, held by new cables as each segment is added. Kigamboni, Dar es Salaam Photo: Miltonisaya / Wikimedia Commons, CC BY-SA 4.0

How much does it cost to cross the Nyerere Bridge?

The bridge is a toll road. Vehicles pay set fees at the toll plaza on the Kigamboni side, with different rates for motorcycles, cars, buses and trucks. Tolls repay the investment of NSSF and the government. Within six years the bridge had collected more than TSh 66 billion in tolls, which shows how heavily it is used. Check current toll rates at the plaza or with the bridge management, since they change from time to time.

How did the bridge change Kigamboni?

The effect on land and housing was fast and clear. Once the drive to the city centre fell to minutes, families, investors and developers moved in. Plot prices rose, and areas like Kibada, Mjimwema, Tungi and Vijibweni filled with new houses, apartments, schools and shops. Our guide to land prices around Dar es Salaam has current ranges.

There were also lessons. Growth outran planning in parts of Kigamboni, leaving narrow access roads, weak drainage and plots on low, sandy ground near creeks that flood. If you build in Kigamboni:

The Nyerere Bridge toll plaza in Vijibweni, Kigamboni, with its row of toll booths under a large sign.
The toll plaza at Vijibweni. Tolls repay the money NSSF and the government put into the bridge. Vijibweni, Kigamboni Photo: Mangapwani / Wikimedia Commons, CC BY-SA 4.0

What can builders learn from the Nyerere Bridge?

The bridge shows that big infrastructure moves property markets. A new bridge, road or railway station can lift land values, but only when the area around it is planned and serviced. For anyone buying land on the strength of a new project, the questions are simple: is the project finished or only planned, is the area surveyed, and will water, power and drainage follow?

It also shows how pension funds can finance infrastructure that pays its own way. The same model has been discussed for other toll roads and bridges. See how Africa pays for infrastructure and Tanzania's mega projects.

Frequently asked questions

How long is the Kigamboni bridge?

About 680 metres.

When did the Nyerere Bridge open?

It opened to traffic in April 2016 and was formally inaugurated on 19 April 2016.

Who paid for the Kigamboni bridge?

NSSF paid about 60 percent and the government about 40 percent. Tolls repay the cost.

Is the Kigamboni ferry still running?

Yes. Ferries still run between Magogoni and Kigamboni and are used by many pedestrians and commuters.

Building in Kigamboni?

Vika Construction builds across Dar es Salaam. Contact us to talk about your plot in Kigamboni or anywhere else in the city.

Found this useful? Share it with someone who is building.

Planning a building project?

Tell us where the site is and what you want built.