The Nyerere Bridge, still widely called the Kigamboni Bridge, is a 680 metre cable-stayed bridge across the Kurasini creek in Dar es Salaam. It links Kurasini on the city side with Kigamboni and opened to traffic in April 2016 after four years of construction. It was built by Chinese contractors China Railway Jiangchang Engineering and China Major Bridge Engineering, designed by Arab Consulting Engineers, and cost roughly US$136 million (about TSh 254 billion with the approach roads). The National Social Security Fund (NSSF) paid about 60 percent and the government about 40 percent, and the bridge recovers its cost through tolls. For people building in Kigamboni, it turned a ferry-dependent peninsula into a place you can drive to from the city in minutes.
Why did Dar es Salaam need the Kigamboni bridge?
Kigamboni sits just across the harbour mouth from the city centre, but for decades the only quick crossing was the ferry from Magogoni. Ferries were crowded, queues were long and breakdowns stranded people. The long road around through Kongowe and Mjimwema took hours in traffic. That held back Kigamboni, even though it had space, beaches and land much cheaper than Masaki or Mikocheni.
A fixed crossing was discussed for years. Work finally started in February 2012, and the bridge opened in April 2016. President Magufuli inaugurated it on 19 April 2016 and named it after Mwalimu Julius Nyerere.
| Fact | Detail |
|---|---|
| Name | Nyerere Bridge (Kigamboni Bridge) |
| Length | About 680 m |
| Type | Cable-stayed bridge |
| Crosses | Kurasini creek, between Kurasini and Kigamboni |
| Built | February 2012 to April 2016 |
| Contractors | China Railway Jiangchang Engineering and China Major Bridge Engineering |
| Designer | Arab Consulting Engineers |
| Cost | About US$136 million (TSh 254 billion including approach roads) |
| Funding | About 60 percent NSSF, 40 percent government |
| Payment | Toll bridge |
How is a cable-stayed bridge built?
A cable-stayed bridge carries its deck on straight cables that run directly from tall towers, called pylons, down to the deck. It suits medium spans like the Kurasini creek, where a ship channel or deep water makes many piers in the water impractical.
The work follows a clear order:
- Deep foundations. In a tidal creek with soft marine soils, the towers and piers sit on large bored piles drilled down to firm ground. Each pile is a steel cage filled with concrete.
- Pile caps and towers. A thick concrete cap ties the piles together. The towers rise from it in stages, cast with climbing formwork.
- Deck segments. The deck is built out from the towers in segments. Each new segment is supported by a new pair of cables before the next goes on, so the deck grows in balance on both sides.
- Cable tuning. Engineers adjust cable forces so the deck sits at the right level and shape.
- Approach roads, toll plaza and finishes. Roads, lighting, barriers and the toll gate at Vijibweni complete the job.

How much does it cost to cross the Nyerere Bridge?
The bridge is a toll road. Vehicles pay set fees at the toll plaza on the Kigamboni side, with different rates for motorcycles, cars, buses and trucks. Tolls repay the investment of NSSF and the government. Within six years the bridge had collected more than TSh 66 billion in tolls, which shows how heavily it is used. Check current toll rates at the plaza or with the bridge management, since they change from time to time.
How did the bridge change Kigamboni?
The effect on land and housing was fast and clear. Once the drive to the city centre fell to minutes, families, investors and developers moved in. Plot prices rose, and areas like Kibada, Mjimwema, Tungi and Vijibweni filled with new houses, apartments, schools and shops. Our guide to land prices around Dar es Salaam has current ranges.
There were also lessons. Growth outran planning in parts of Kigamboni, leaving narrow access roads, weak drainage and plots on low, sandy ground near creeks that flood. If you build in Kigamboni:
- Check the plot in the rains. Some low areas flood. See protecting a building from flooding.
- Test the soil. Sandy coastal soils and pockets of soft clay need the right foundation. See soil testing.
- Build for the coast: dense concrete, good steel cover, coated roofing. See building near the coast.
- Confirm the title. Fast price rises brought more land disputes. See checking a land title.

What can builders learn from the Nyerere Bridge?
The bridge shows that big infrastructure moves property markets. A new bridge, road or railway station can lift land values, but only when the area around it is planned and serviced. For anyone buying land on the strength of a new project, the questions are simple: is the project finished or only planned, is the area surveyed, and will water, power and drainage follow?
It also shows how pension funds can finance infrastructure that pays its own way. The same model has been discussed for other toll roads and bridges. See how Africa pays for infrastructure and Tanzania's mega projects.
Frequently asked questions
How long is the Kigamboni bridge?
About 680 metres.
When did the Nyerere Bridge open?
It opened to traffic in April 2016 and was formally inaugurated on 19 April 2016.
Who paid for the Kigamboni bridge?
NSSF paid about 60 percent and the government about 40 percent. Tolls repay the cost.
Is the Kigamboni ferry still running?
Yes. Ferries still run between Magogoni and Kigamboni and are used by many pedestrians and commuters.