In 2026, typical daily rates for building tradespeople in Dar es Salaam are roughly TSh 30,000 to 50,000 for a skilled fundi (mason, carpenter, welder, tiler, plumber or electrician) and TSh 12,000 to 20,000 for a helper (msaidizi). Rates in regional towns are often 10 to 30 percent lower. Many finishing jobs are priced per square metre instead: tiling about TSh 8,000 to 15,000 per m², plastering about TSh 4,000 to 7,000 per m², and painting about TSh 2,000 to 4,000 per m² in labour. Rates vary with skill, location, job size and who supplies tools, so use these as a guide and agree the price, scope and payment stages in writing before work starts.
What do fundis charge per day?
| Trade | Dar es Salaam (TSh per day) | Regional towns (TSh per day) |
|---|---|---|
| Fundi mkuu (lead mason) | 40,000 to 60,000 | 30,000 to 45,000 |
| Mason (fundi mwashi) | 30,000 to 45,000 | 25,000 to 35,000 |
| Carpenter | 30,000 to 50,000 | 25,000 to 40,000 |
| Steel fixer | 30,000 to 45,000 | 25,000 to 35,000 |
| Welder | 35,000 to 60,000 | 30,000 to 45,000 |
| Electrician | 35,000 to 60,000 | 30,000 to 45,000 |
| Plumber | 35,000 to 55,000 | 30,000 to 45,000 |
| Helper (msaidizi) | 12,000 to 20,000 | 10,000 to 15,000 |
Rates are indicative for 2026 and vary by skill, demand and season. They usually cover labour only, not materials.
What are typical per square metre rates?
| Job | Labour rate (TSh per m², approx.) |
|---|---|
| Blockwork | 3,000 to 6,000 |
| Plastering (internal or external) | 4,000 to 7,000 |
| Floor screed | 3,000 to 6,000 |
| Floor tiling | 8,000 to 15,000 |
| Wall tiling | 10,000 to 18,000 |
| Painting (two coats plus prep) | 2,000 to 4,000 |
| Gypsum ceiling | 8,000 to 15,000 |
| Roofing (sheets on prepared structure) | 3,000 to 6,000 |
Large-format tiles, patterns, high walls, scaffolding and difficult access cost more.

Daily rate, per m², or lump sum: which is better?
| Method | Good for | Risk |
|---|---|---|
| Daily rate | Small repairs, unclear scope | Slow work costs you more |
| Per m² or per item | Plaster, tiles, paint, blockwork | Quality can drop if rushed; inspect each area |
| Lump sum per stage | Whole house stages with clear drawings | Disputes if scope is unclear |
| Contractor | Full projects | Higher headline price, but managed and responsible |
For a full house, many people pay a fundi per stage (foundation, walls to ring beam, roofing, finishes). Write down exactly what each stage includes. See fundi or registered contractor and contracts with fundis.
How do I agree pay without disputes?
- Agree the scope in writing: rooms, areas, what is included.
- Agree who supplies tools, water and minor materials.
- Measure areas together before and after the work.
- Pay in stages linked to work you have seen and checked.
- Keep receipts and records of each payment, even via mobile money.
- Hold back a small amount until defects are fixed.
What else adds to labour cost?
- Transport and lunch allowances, often expected on top of daily rates.
- Overtime and weekend work.
- Supervision: someone needs to check quality.
- Rework when jobs are done badly.
See hidden costs of building a house.
How long do common jobs take a fundi crew?
| Job | Typical output per crew per day |
|---|---|
| Blockwork (mason plus helper) | 8 to 15 m² |
| Internal plaster (mason plus helper) | 15 to 25 m² |
| Floor tiling (tiler plus helper) | 10 to 20 m² |
| Painting, two coats (one painter) | 30 to 60 m² |
| Screeding (crew of three) | 30 to 60 m² |
Outputs vary with access, weather, wall heights and the quality required. Use them to check whether a time estimate is realistic, and to compare daily-rate and per-m² prices. If a fundi on a day rate lays only 4 m² of tiles a day, the job is costing you far more than a per-m² price would.
Rates change with demand. During busy periods, such as dry seasons and before holidays, good fundis are booked up and prices rise. Planning work early and booking reliable people in advance often saves money and time.
Frequently asked questions
How much is a fundi paid per day in Tanzania?
Skilled fundis often earn TSh 30,000 to 50,000 a day in Dar es Salaam in 2026, less in smaller towns.
How much does tiling cost per square metre?
Labour is often TSh 8,000 to 15,000 per m², plus tiles and adhesive.
Is it cheaper to hire fundis or a contractor?
Fundis often look cheaper, but without supervision costs can rise through waste and rework. Contractors carry responsibility for the result.
Should I pay fundis weekly?
Paying weekly against measured work, with a final retention, works well for many owners.
Do fundis charge for travel and food?
Many expect transport and lunch allowances on top of the daily rate. Agree this before starting.
Are rates higher on weekends?
Often yes. Weekend and night work may be charged at a higher rate.
How do I find a reliable fundi?
Ask to see finished work, talk to previous clients, start with a small job, and check whether they have VETA training or a registered contractor behind them. See how to become a well-paid fundi.
Is it better to pay per stage or per day?
Per stage or per m² works best for clear jobs. Daily rates suit small, unclear repairs.
Do I pay a helper separately from the fundi?
Usually yes. Agree whether the fundi's price includes helpers or whether you pay them directly, so nobody is left unpaid.