Door and window frames must be fixed plumb (vertical), square and level, firmly anchored into the wall, and sealed against rain. In Tanzania, steel and timber frames are often built into the wall as the blocks go up, using fixing lugs or hoop iron set in the mortar joints. Aluminium and uPVC windows are usually fitted later into finished openings with screws, anchors and sealant. The most common problems, such as doors that stick, gaps that let in light and rain, and cracks around frames, come from frames that were not braced while the wall was built, openings that were not square, too few fixings, and missing lintels or sealant.
When should frames be installed?
| Frame type | When to fit | How it is fixed |
|---|---|---|
| Steel door frames | As walls are built | Lugs bedded in mortar, frame filled with mortar |
| Timber door frames | As walls are built or after plaster | Hold-fast lugs or screws and plugs |
| Steel window frames | As walls are built | Lugs in mortar joints |
| Aluminium windows and doors | After plaster, before final paint | Screws and anchors through sub-frame, sealant |
| uPVC windows | After plaster | Frame fixings and foam, sealant |
Fitting aluminium and uPVC late keeps them clean and undamaged. Plan the openings to the window maker's sizes before the walls go up. See doors and windows.
How do I fix a frame plumb and square?
- Check the opening for size, square (measure both diagonals; they should match) and level sill.
- Set the frame on packers so the bottom is level and at the right height for the finished floor.
- Plumb both sides with a spirit level in two directions.
- Check diagonals of the frame. Adjust until they are equal.
- Brace frames that are built in, with timber struts, so they cannot move as blocks are laid or concrete is poured.
- Fix at enough points: usually at least three on each side for doors and two or three for windows, plus the head on wide openings.
- Recheck before the mortar or fixings set.

How do I stop windows leaking?
Leaks usually come at the joint between frame and wall, not through the glass. To prevent them:
- Fit a sloping sill that throws water clear of the wall, with a drip groove underneath.
- Seal the frame to the wall with a good exterior sealant, continuous all round.
- Keep weep holes clear on aluminium windows so water inside the frame drains out.
- Flash or set back windows in exposed walls so driving rain does not hit the joint directly.
- Check after the first rains and reseal any gaps.
See waterproofing roofs and walls.
Why do doors stick or drop?
| Symptom | Likely cause |
|---|---|
| Door rubs at the top | Frame not plumb, or lintel sagging |
| Gap widening at the side | Frame not fixed firmly, moved during building |
| Door swings open or shut by itself | Hinges not in line, frame twisted |
| Timber door sticks in rainy season | Unsealed timber swelling |
| Cracks around frame | Too few fixings, or no lintel over the opening |
A lintel over every opening protects the frame from the load of the wall above. See lintels and ring beams.

What are the fixing details for each frame type?
| Frame | Typical fixing | Watch out for |
|---|---|---|
| Pressed steel door frame | Lugs in mortar joints, frame back-filled with mortar | Fill the frame fully so it does not sound hollow or dent |
| Timber door frame | Hold-fast lugs or screws into plugs, at least 3 per side | Treat and prime all faces before fixing |
| Steel window | Lugs in joints, sill bedded in mortar | Rust protection before building in |
| Aluminium window | Screws through sub-frame or frame into plugs, sealant all round | Do not overtighten and twist the frame |
| uPVC window | Frame fixings and expanding foam, sealant outside | Foam alone is not a fixing |
How should openings be prepared?
Ask the mason to build openings to exact sizes and keep them square, with straight reveals and a level sill. Aluminium window makers usually measure finished openings after plastering and make windows to fit, with a gap of about 5 to 10 mm all round for fixing and sealant. Large gaps filled with mortar or foam are a sign the opening was built badly.
When should frames be checked?
Check frames for plumb and square before the wall goes higher, again before plastering, and once more before hanging doors. A frame that has moved is easy to correct before plaster and very hard afterwards.
When frames arrive on site, store them flat or upright on timber, under cover and away from mixing areas. Bent steel frames and scratched aluminium are hard to fix once built in, and cement splashes on aluminium leave permanent marks.
Frequently asked questions
Should door frames be fixed before or after plaster?
Built-in steel and timber frames go in as walls rise. Aluminium and uPVC are fitted after plastering.
How many fixings does a door frame need?
At least three on each side, more for heavy doors.
What gap should be left around a door?
About 2 to 3 mm at the sides and top, more at the bottom for floor finishes and airflow.
Why does my window leak when it rains?
Usually the seal between frame and wall, a missing drip on the sill, or blocked weep holes.
What sealant should I use around windows?
A good exterior-grade silicone or polyurethane sealant that stays flexible. Avoid cheap sealants that crack and shrink in the sun.
Can a door frame be fixed after the wall is plastered?
Yes, timber and some steel frames can be fixed into finished openings with frame screws or anchors. Leave a small gap and fill it neatly.
Why are there cracks above my door?
Usually a missing or short lintel, or the frame was not fixed firmly. See lintels and ring beams.