
Building a church or mosque means building a large, open hall that must stay cool, carry sound well and last for generations, usually funded by a community over several years. Plan about 0.6 to 1.0 m² of floor space per seated worshipper in the main hall, plus space for aisles, the altar or mihrab, and ancillary rooms. Large halls need roofs that span 12 to 20 metres or more without columns, so they need steel trusses or portal frames designed by an engineer. Good cross ventilation, high ceilings, shaded walls and a sound system planned with the building make the space comfortable. Building in clear phases, each finished and usable, avoids half-built structures that decay while funds are raised.
How big should the hall be?
| Item | Typical allowance |
|---|---|
| Seated worshipper (pews or chairs) | 0.6 to 0.8 m² |
| Worshipper on prayer mats (mosque) | about 0.8 to 1.0 m² per person in rows |
| Aisles and circulation | Add 20 to 30% |
| Altar, choir, mimbar or mihrab area | As the design needs |
| Entrance, ablution, offices, stores, toilets | Separate rooms, often 20 to 40% extra |
Example. A church for 500 seated people needs about 300 to 400 m² of seating, plus aisles and the altar area, so a hall of around 450 to 550 m², for example 18 by 28 metres.
For mosques, the prayer hall is usually oriented towards the qibla, and ablution areas need proper water supply and drainage.
How do you span a large roof?
Ordinary house trusses are not enough for halls of 15 metres and wider. Options:
| Roof structure | Span | Notes |
|---|---|---|
| Steel trusses | 12 to 25 m | Common, economical, need design and good fixing |
| Steel portal frames | 15 to 40 m | Clear spans, used in warehouses and large halls |
| Reinforced concrete frame with steel roof | Any | Concrete columns and ring beams carry steel trusses |
| Timber trusses | Up to about 12 m | Cheaper but need treatment and design |
Large roofs catch a lot of wind. They must be tied down properly and braced. See roof trusses and steel frame buildings.

How do I keep a large hall cool and audible?
Heat. A large iron roof over hundreds of people gets very hot. Use:
- high ceilings and roof vents to let hot air out,
- many windows or openings on opposite walls for cross ventilation,
- ceiling insulation or an insulated roof,
- deep overhangs and verandas to shade walls.
Sound. Bare concrete, glass and iron sheets bounce sound, making speech hard to follow. Help it with:
- a ceiling with some sound-absorbing boards,
- a properly designed sound system with speakers spread along the hall,
- avoiding long parallel hard walls where possible.
See how to keep a building cool.
What permits are needed?
- A building permit with architectural and structural drawings.
- Land title or a formal right to the plot in the name of the registered religious body.
- Fire safety approval for a building where many people gather. See fire safety in buildings.
- For large projects, an environmental review may apply.
How do we build in phases?
Many congregations build over years. Plan phases so each one ends with something usable and protected:
- Phase 1: foundations and floor slab for the full building, plus temporary roof or use as an open-air space.
- Phase 2: columns, walls to ring beam, and the full roof. Once roofed, the hall can be used.
- Phase 3: windows, doors, plaster and floor finishes.
- Phase 4: ceilings, sound, lighting, decoration and external works.
Get the full design and structural drawings before Phase 1, so foundations suit the final building. See building in phases.

What extra rooms and services do places of worship need?
| Space or service | Notes |
|---|---|
| Toilets | Enough for peak attendance, with separate facilities for men and women |
| Ablution area (mosques) | Running water, good drainage and non-slip floors |
| Offices and stores | For records, equipment and instruments |
| Sound room or control desk | Central position with a clear view of the front |
| Parking and drop-off | Space for cars, motorbikes and buses on busy days |
| Accessibility | Ramps and wide doors for elderly and disabled worshippers |
How do we manage community fundraising and building?
- Appoint a small building committee with clear roles and a treasurer.
- Get a professional design and bill of quantities before raising funds, so donors see what each phase costs.
- Pay contractors and fundis against measured work, with receipts.
- Keep simple accounts that the congregation can see.
- Buy major materials in bulk when funds allow, and store them securely.
A transparent process keeps donors giving and avoids disputes that stop projects halfway.
Frequently asked questions
How much does it cost to build a church in Tanzania?
Large halls often cost in the same range per m² as commercial buildings, with the roof structure and finishes making the biggest difference. Get a bill of quantities for each phase so the community knows what each stage needs.
Can a hall be built without columns inside?
Yes, with steel trusses or portal frames designed for the span.
How many people fit in a 20 by 30 metre hall?
Roughly 700 to 900 seated, depending on layout and aisles.
Do places of worship need fire exits?
Yes. Any building where many people gather needs enough exits, clear routes and extinguishers.
What floor finish suits a large hall?
Terrazzo, polished concrete and large porcelain tiles are durable and easy to clean. Choose non-slip finishes near entrances and ablution areas.
How high should the ceiling of a large hall be?
Often 4 to 6 metres or more, which helps hot air rise away from people and improves the feeling of space.
Planning a place of worship or community hall?
Vika Construction builds large halls, schools and public buildings. Contact us to talk about your project.
Found this useful? Share it with someone who is building.


