Choosing Sand and Aggregate (Kokoto) in Tanzania: River, Pit, Sea Sand and Stone Sizes

Dirty sand and the wrong stone size weaken concrete more than most people realise. Which sand and kokoto to buy for each job, and simple tests you can do on site.

Workers shovelling sand from a large heap on a building site in Kenya.
Kenya Photo: Mugambi Muriuki / Wikimedia Commons, CC BY-SA 4.0
Share

For concrete, use clean, sharp, well-graded sand (often river sand or washed pit sand) and crushed stone aggregate (kokoto) of about 20 mm maximum for slabs, beams and columns, or 10 to 14 mm for thin sections. For mortar and plaster, use clean building sand that is finer but not dusty or full of clay. Never use sea sand or beach sand in structural work because the salt corrodes steel. Before accepting a load, do a simple silt test in a bottle: if more than about 6 to 8 percent of the sand settles as a layer of mud, it needs washing or rejecting. Buy by the cubic metre and measure the load on arrival.

What types of sand are sold in Tanzania?

SandWhere fromGood forWatch out for
River sandRiverbedsConcrete, mortarCan be scarce or restricted; check permits
Pit sandInland pitsMortar, plaster, sometimes concreteOften has clay or silt, may need washing
Crushed stone sand (quarry dust)QuarriesConcrete, blocksCan be dusty and harsh; blend or wash
Sea or beach sandCoastNot for buildingSalt corrodes steel; extraction often illegal
Plaster sandSieved pit or river sandPlaster, screedMust be clean and fine

In some areas, local authorities control where sand can be mined. Buy from licensed suppliers, both for quality and to avoid problems. See sand and kokoto business.

What size of aggregate (kokoto) should I use?

SizeSwahili trade name (common)Use
6 to 10 mmKokoto ndogo, chippingsThin slabs, toppings, block making
10 to 14 mmKokoto ndogoThin sections, precast items
20 mmKokoto ya katiMost structural concrete
25 to 40 mmKokoto kubwaMass concrete, foundations
Hardcore 100 to 200 mmKifusiFill under slabs

Crushed stone gives better grip with cement than smooth round gravel. Mixed sizes pack better and need less cement.

Workers filling buckets from a heap of crushed stone aggregate in Kenya.
Kokoto comes in several sizes. Most structural concrete uses 20 mm crushed stone. Kenya Photo: Mugambi Muriuki / Wikimedia Commons, CC BY-SA 4.0

How do I test sand quality on site?

Bottle silt test

  1. Fill a clear bottle about a third with sand.
  2. Add water to about two-thirds, plus a pinch of salt.
  3. Shake hard and leave for an hour or more.
  4. Measure the layer of fine mud on top of the sand.
  5. If the mud layer is more than about 6 to 8 percent of the sand height, the sand is too dirty for good concrete.

Hand test: rub damp sand in your palm. Clean sand leaves your hand almost clean. Clay or silt leaves a stain.

Taste or look for shells: salty taste or shell pieces suggest sea sand. Reject it for structural work.

How do I check aggregate quality?

  • Stones should be hard, angular and clean, not crumbly or coated in dust and clay.
  • No organic matter, roots or rubbish.
  • A reasonable mix of sizes.

How do I buy sand and aggregate?

  1. Ask for the price per cubic metre and the volume of the truck.
  2. Measure the load: length × width × average height.
  3. Inspect before tipping if possible.
  4. Store on a hard, clean surface, separate from soil and each other.
  5. Cover sand from rain and wind if it will sit a long time.

How much sand and aggregate does a house need?

For a simple 120 m² single-storey house, rough quantities are:

UseSandAggregate
Concrete (foundations, slab, columns, beams)12 to 18 m³25 to 35 m³
Block laying mortar3 to 4 m³
Plaster (inside and outside)10 to 15 m³
Floor screed4 to 6 m³
Hardcore fill under slab15 to 25 m³ hardcore

Exact figures come from the bill of quantities. See concrete quantities and building materials list.

Can I wash dirty sand on site?

Yes, for small amounts. Spread sand on a sloping hard surface or in a sieve and wash it with plenty of water until the run-off is clear, then let it drain. It takes time and water, so for large jobs it is usually cheaper to buy clean sand. Never wash sand where the dirty water will run into neighbours' plots or drains.

What about quarry dust?

Crushed stone dust from quarries is widely used in blocks and concrete. It can be good, but it is often too fine and dusty on its own. Blending it with natural sand or washing it improves concrete. Check the mix with trial batches and cube tests on structural work. See concrete cube testing.

If you find a good supplier, stick with them. Consistent sand and aggregate from one source make concrete and plaster easier to control, and a supplier who values your repeat business is less likely to send poor loads.

Frequently asked questions

Can I use beach sand for building?

No. Salt corrodes steel and weakens concrete, and beach sand extraction is often illegal.

What is the best sand for plastering?

Clean, fine, well-graded sand free of clay, often sieved river or pit sand.

What size kokoto is used for slabs?

Usually 20 mm crushed stone.

How do I know if sand is too dirty?

Do the bottle silt test. More than about 6 to 8 percent mud means wash or reject it.

What is the difference between sand and quarry dust?

Sand is natural, formed by rivers or weathering. Quarry dust is crushed stone, more angular and often finer and dustier.

Can I use red pit sand for concrete?

Only if tests show it is clean enough. Red colour often comes from iron and clay, and high clay content weakens concrete.

How should sand be stored on site?

On a clean hard base, away from soil, covered from rain and wind, and separate from aggregate.

Why does my plaster crack when the sand looked fine?

Fine silt and clay you cannot see easily, or too much cement and water. Do the bottle test before buying.

Want quality materials on your project?

Vika Construction checks and tests materials on every site. Contact us, or read concrete grades explained.

Found this useful? Share it with someone who is building.

Planning a building project?

Tell us where the site is and what you want built.