To select a contractor for a large commercial project, run a structured process: define the project and procurement route, prequalify contractors on registration, experience, capacity and finances, shortlist four to six firms, issue complete tender documents, hold a site visit and clarification period, evaluate bids on both technical quality and price using a scoring matrix agreed in advance, interview the top bidders and their site teams, check references and visit their projects, then negotiate and award with guarantees, insurance and a signed contract in place. For banks, hospitals, schools, offices, hotels, warehouses and property developers, this process protects the budget and gives the board a clear record of why the contractor was chosen.
A small house can be awarded on trust and a handshake. A TSh 5 billion office block cannot.
Step 1: Define the project and how you will buy it
Before contacting any contractor, the client and design team should agree:
- the scope, budget and target completion date
- the procurement route: traditional (design first, then tender), design and build, or management contracting
- the form of contract
- whether the price will be a lump sum, a remeasured BOQ, or cost plus a fee
- whether public procurement rules apply (government, parastatals and many donor-funded projects must follow the Public Procurement Act and PPRA rules, through NeST; see public procurement explained)
Getting this wrong at the start leads to bids that cannot be compared.
Step 2: Prequalify contractors
Prequalification checks basic ability before anyone spends time pricing. Ask interested contractors for:
| Criterion | What to ask for |
|---|---|
| Registration | CRB category and class for the contract value |
| Experience | Similar projects in the past 5 to 10 years, with values and clients |
| Capacity | Current workload, staff, equipment |
| Finance | Audited accounts for 3 years, turnover, credit lines |
| Safety | HSE policy, safety record, safety officer |
| Quality | Quality system, sample test plans |
| Legal | Tax clearance, no blacklisting or disputes |
Set pass marks in advance. A company that fails a mandatory criterion should not be shortlisted however good the rest looks.
Step 3: Shortlist four to six contractors
Fewer than four may not give real competition. More than six wastes everyone's time and discourages good contractors, who know the odds are poor. Choose firms that have done buildings of similar type and size.

Step 4: Issue complete tender documents
Incomplete documents produce bids full of assumptions, which turn into variations later. A good tender package includes:
- instructions to tenderers and the deadline
- form of contract and conditions
- drawings: architectural, structural, services
- specifications
- bill of quantities (BOQ explained)
- programme requirements and key dates
- forms for method statements, staff, equipment and programme
- evaluation criteria and weighting
See our tender documents checklist.
Step 5: Site visit and clarifications
Hold a site visit for all tenderers together. Record every question and send answers to all bidders in writing, so nobody gets an advantage. Allow enough time to price properly: three to six weeks for a large building is common.
Step 6: Evaluate on quality and price
Price matters, but the lowest bid is often the riskiest. Use a scoring matrix agreed before bids are opened, for example:
| Criterion | Weight |
|---|---|
| Price | 50 to 70% |
| Methodology and programme | 10 to 20% |
| Key staff | 10 to 15% |
| Relevant experience | 5 to 15% |
| HSE and quality plans | 5 to 10% |
Check the priced BOQ line by line. Look for:
- arithmetic errors
- unusually low rates on items that matter, such as concrete, steel and waterproofing
- front-loading, where early items are overpriced to get cash early
- missing items or provisional sums
- qualifications that change the scope
A bid more than about 10 to 15% below the pre-tender estimate deserves a careful conversation, not an immediate award. See comparing contractor quotations.
Step 7: Interview the top two or three
Meet the people who will run the job, not only the directors. Ask the proposed project manager and site engineer to walk you through:
- how they will sequence the work
- the biggest risks they see and how they will handle them
- how they will keep the site safe in a busy area
- how they will report progress
- how they handle variations and delays
You learn quickly who has read the drawings.

Step 8: Check references and visit projects
Call at least two past clients for each of the top bidders. Ask:
- Did the project finish on time and on budget? If not, why?
- How did the contractor handle problems and variations?
- How were safety and site tidiness?
- Would you hire them again?
Visit a current site. Look at the stores, safety signs, housekeeping and records. A site run well today is the best predictor of how yours will be run. Our guide to assessing contractor experience and capacity lists more checks.
Step 9: Negotiate, award and sign
Before signing:
- clarify any qualifications in the bid and agree them in writing
- confirm the programme and key staff as contract commitments
- receive the performance guarantee (often 10% of the contract value) and advance payment guarantee if an advance is paid
- confirm insurance: contractor's all risks, third-party, workers' compensation
- agree retention, payment periods and the defects liability period
- sign the contract and issue the formal letter of award
Then hold a start-up meeting to agree reporting, site rules and communication. See our contract checklist.
How long does contractor selection take?
| Stage | Typical time |
|---|---|
| Prequalification | 2 to 4 weeks |
| Tender period | 3 to 6 weeks |
| Evaluation and interviews | 2 to 4 weeks |
| Negotiation and signing | 1 to 3 weeks |
| Total | About 2 to 4 months |
Public tenders often take longer because of statutory periods and approvals. Build this time into the overall project programme.
Special points for different clients
- Banks: security, strongrooms, IT and branding standards; contractors with bank experience understand these. See bank branch construction.
- Schools: phasing around term dates and child safety. See building a school.
- Hospitals: infection control, medical gases and working in live facilities. See hospital construction.
- Developers: speed, cash flow and sales handover dates.
- Warehouses and factories: large floor slabs, steel frames and heavy civil works. See factory construction.
When is a negotiated or single-source contract acceptable?
Private clients sometimes skip competitive tendering and negotiate directly with one contractor. That can be sensible when:
- the contractor already built an earlier phase and knows the site and systems
- the work is urgent, for example after a fire or flood
- the project needs specialist experience few companies have
- the client wants the contractor involved early in design to control cost and buildability
The risk is price. Without competition, you have no market check. Protect yourself by having an independent quantity surveyor prepare a pre-tender estimate, agreeing an open-book price with the contractor's rates and margins visible, and benchmarking key rates against recent tenders. Public bodies can only use single-source procurement in the limited cases the procurement law allows.
Warning signs during the tender
- A bidder asks for drawings that were already issued, close to the deadline. They may not be pricing seriously.
- A bid arrives with large parts of the BOQ left blank or marked "included".
- The proposed site team is the same group already named on three other live projects.
- References are only friends or relatives of the company's directors.
- A contractor offers to "help" with the evaluation or contacts board members directly.
Mistakes to avoid
- Awarding on price alone.
- Changing the evaluation criteria after bids open.
- Allowing bidders to negotiate separately before evaluation.
- Not checking that key staff are actually available.
- Signing without guarantees in hand.
- Starting work on a letter of intent with no agreed contract.
Frequently asked questions
Should I always choose the lowest bid?
No. Choose the bid that gives the best value once quality, programme and risk are considered. Many private clients award to the lowest compliant bid that passes the technical evaluation.
How many contractors should I invite to tender?
Four to six prequalified contractors usually gives real competition without wasting effort.
What is prequalification?
A first stage where contractors show they meet minimum requirements for registration, experience, finances and capacity before they are invited to price.
Can I negotiate with contractors after tenders close?
Private clients can negotiate with the preferred bidder once evaluation is done. Public bodies must follow PPRA rules on negotiation.
Do I need a consultant to run the process?
For large projects, a quantity surveyor or project manager usually runs the tender, prepares documents and evaluates bids, which saves far more than it costs.
What is a letter of award?
A formal letter telling the successful contractor they have won the contract, usually subject to providing guarantees and signing the contract within a set time.
What if the preferred contractor cannot provide a performance guarantee?
Treat it as a warning about their financial standing. Either move to the next-ranked bidder or agree a short deadline. Starting work without the guarantee leaves you exposed if the contractor fails.