Building a house in Zanzibar is different from building on the mainland in three ways. Zanzibar has its own land laws and its own permit system, run by the Development Control Unit (DCU) under the Department of Urban and Rural Planning, with separate rules for Stone Town. Much of the island sits on coral limestone, so builders use cut coral stone blocks alongside cement blocks. And sand is scarce and tightly controlled, which pushes up its price. You will need a legal right to the land, approved drawings and a building permit before work starts. In 2026 most family houses on Unguja cost around TSh 800,000 to 1,500,000 per m², a little more than Dar es Salaam because many materials cross by sea.
Who can own land and build in Zanzibar?
All land in Zanzibar belongs to the government, and people hold rights to use it. Zanzibaris can get a right of occupancy for residential land through the land authorities. Mainland Tanzanians and foreigners face more limits. Foreign buyers can usually only buy within approved investment projects registered with ZIPA, the Zanzibar Investment Promotion Authority, and new rules require real estate projects to register with ZIPA before they market or sell units.
Before you pay for any plot:
- Confirm the seller has a registered right to the land, not just a village letter.
- Check the plot with the land registry and the planning department.
- Make sure the land use plan allows a house on that plot.
- If you are not Zanzibari, take legal advice. Read our Zanzibar property investment guide and can foreigners own land in Tanzania.
How do I get a building permit in Zanzibar?
Building permits in Zanzibar are issued by the DCU. You submit an application with architectural and structural drawings, proof of your land right, a site plan and the fees. Recent rules also ask for the contractor's contract to be submitted with the application. Investor projects must include the ZIPA investment certificate. The DCU publishes guidelines with drawing rules and a checklist, and following them closely speeds things up.
Stone Town is a separate case. It is a UNESCO World Heritage Site, and all building work there needs permission from the Stone Town Conservation and Development Authority. See our guide to Stone Town building rules.
| Location | Permit body | Extra rules |
|---|---|---|
| Stone Town | Stone Town Conservation and Development Authority | Conservation guidelines, lime plaster, no extra floors |
| Zanzibar town (Ng'ambo, Mjini) and suburbs | DCU, Department of Urban and Rural Planning | Zoning, setbacks, height limits |
| Coastal tourism areas | DCU, plus ZIPA for investors | Beach setbacks, environmental approval for hotels |
| Pemba | Planning and council offices in Pemba | Same law, local offices |

What materials do builders use in Zanzibar?
Zanzibar sits on coral limestone, and builders have used it for centuries. Today the common walling choices are:
- Cut coral stone blocks. Sawn from coral quarries, light, cheap and good at keeping houses cool. They are porous, so they need good plaster and a damp proof course.
- Cement sand blocks. Made locally, but they need a lot of sand, which is scarce.
- Coral rag in lime mortar. The traditional Stone Town method, now mostly used in heritage repairs.
Sand is the problem material. Uncontrolled sand mining damaged land and beaches, so the government restricts where sand can be taken, and prices are high. Some builders bring sand and aggregate from the mainland. Cement, steel and roofing sheets mostly come by ship from Dar es Salaam, which adds cost and time.
How do I protect a Zanzibar house from salt, damp and wind?
Zanzibar is hot, humid and salty all year. To make a house last:
- Use dense concrete with deep cover over steel, at least 40 mm on outside faces.
- Use washed sand and fresh water in concrete. Salt in the mix rusts steel from inside.
- Choose coated roofing and stainless or galvanised fixings, and tie the roof down well. The coast gets strong winds. See cyclones on the Tanzanian coast.
- Add a damp proof course and membrane, because porous coral walls draw water up from the ground.
- Treat for termites before the slab. See termite protection.
Our guide to building near the coast covers this in more depth.
How much does it cost to build a house in Zanzibar?
In 2026 most family houses on Unguja cost about TSh 800,000 to 1,500,000 per m². Shipping cement, steel and finishes from Dar es Salaam adds cost, and sand is expensive. Labour is similar to the mainland. Coral stone walling can save money compared with cement blocks. A 120 m² three-bedroom house is roughly TSh 100 million to 180 million. Pemba can be cheaper for labour but more expensive for materials. See the cost of building a house in Tanzania.

Where are people building in Zanzibar?
Most new homes go up in the growing suburbs around Zanzibar town, such as Mbweni, Fumba, Tunguu and the areas along the airport and Bububu roads. The new town at Fumba, the Amaan and Fumba stadium works for AFCON 2027 and new hotels on the east coast all bring workers and demand for rental housing. See AFCON 2027 host cities and short-let apartments in Zanzibar.
Frequently asked questions
Can a mainland Tanzanian buy land in Zanzibar?
The rules are stricter than for Zanzibaris. Many mainlanders buy through approved projects or long leases. Get legal advice and check with the land authorities before paying.
Are coral stone blocks strong enough for a house?
Yes for single-storey walls carrying normal roof loads, when the house has a concrete frame or ring beam. For storey houses, the engineer usually specifies a concrete frame with coral or cement block infill.
Why is sand so expensive in Zanzibar?
Sand mining is restricted to protect land and beaches. Supply is limited and some sand comes from the mainland.
How long does a building permit take in Zanzibar?
For investors the DCU aims to decide within seven working days of a complete application. Ordinary applications can take longer. Complete drawings and documents help a lot.