Building a petrol station in Tanzania needs approvals before any construction starts: a building permit from the council, an Environmental Impact Assessment certificate from NEMC, and construction approval from EWURA, the Energy and Water Utilities Regulatory Authority, which also issues the operating licence once the station is built and inspected. A typical station has underground fuel tanks, a forecourt with pump islands under a steel canopy, a small shop and office, toilets, and oil and water separators for drainage. Costs vary widely with land, tank capacity and finishes, but a complete small to medium station often runs from several hundred million to over a billion shillings. Safety, spill control and correct tank installation are the core of the design.
What approvals does a petrol station need?
| Approval | From | When |
|---|---|---|
| Land use and title for a filling station | Land office and council | Before design |
| Building permit | Local council | Before construction |
| Environmental Impact Assessment certificate | NEMC | Before construction |
| Construction approval for petroleum facility | EWURA | Before construction |
| Fire safety approval | Fire and Rescue Force | During and after construction |
| Operating licence | EWURA | After inspection, before selling fuel |
| Business licence and other permits | Council and other agencies | Before opening |
Requirements and fees change, so check the current EWURA rules and guidelines before buying land. See EIA for construction.
How do I choose a site?
- Traffic and access: a busy road with safe entry and exit, not too close to junctions.
- Plot size: enough room for tanker deliveries and vehicles to queue without blocking the road. Many stations need at least about 1,500 to 3,000 m², depending on layout.
- Distance rules: separation from schools, hospitals, residential buildings and water sources as set by regulators.
- Ground conditions: high ground water and flood-prone land make tank installation harder and riskier.
- Utilities: power, water and drainage.
What are the main parts of a station?
- Underground storage tanks: double-walled steel or fibreglass tanks, often 20,000 to 60,000 litres each, set in a concrete pit or bedded in sand with anchoring against flotation.
- Pipework and vents: from tanks to dispensers, with leak detection and vent pipes at safe heights.
- Forecourt: reinforced concrete slab with falls to drains, resistant to fuel.
- Pump islands and dispensers.
- Canopy: steel structure with lighting, covering the pump islands.
- Building: shop, office, store, toilets, sometimes a lube bay or car wash.
- Drainage: oil and water interceptor before any water leaves the site.
- Fire safety: extinguishers, sand buckets, emergency stops and signage.

What does a petrol station cost?
| Item | Share of construction cost (approx.) |
|---|---|
| Tanks, pipework and installation | 25 to 35% |
| Forecourt slab and drainage | 15 to 20% |
| Canopy and lighting | 10 to 15% |
| Dispensers and equipment | 10 to 20% |
| Shop and service building | 10 to 20% |
| Approvals, design, EIA, fees | 5 to 10% |
Land is extra and often the largest single cost on a good road. Get a full bill of quantities from a contractor and an equipment quote from suppliers.

How long does it take?
Approvals often take several months. Construction of a small to medium station usually takes 4 to 8 months, depending on tanks, canopy fabrication and site conditions.
What safety features must be built in?
| Feature | Purpose |
|---|---|
| Double-walled tanks and leak detection | Catch leaks before fuel reaches the ground |
| Spill containment at fill points | Contain spills during tanker deliveries |
| Emergency stop buttons | Cut power to dispensers quickly |
| Earthing and bonding | Prevent static sparks during deliveries |
| Fire extinguishers and sand buckets | First response to small fires |
| Vent pipes at safe heights | Release vapour away from people and buildings |
| Oil and water interceptor | Stop fuel entering drains and soil |
| No-smoking and phone signs | Reduce ignition risks |
Staff training matters as much as the equipment. Every attendant should know how to use the emergency stop and extinguishers. See fire safety in buildings.
How is a station laid out?
Most layouts put pump islands under the canopy near the road, with a one-way flow: cars enter, fuel and leave without reversing. Tanker parking and the fill points sit to one side where the tanker can stand clear of customer traffic. The shop and office face the forecourt so staff can see the pumps. Toilets, air and water points and any car wash go towards the back. A good layout reduces queues and accidents, and makes approvals easier.
Build a realistic programme that includes approvals, tank delivery, canopy fabrication and inspections. Equipment and tanks are often imported or made to order, so ordering them early keeps the opening date on track.
Frequently asked questions
Who licenses petrol stations in Tanzania?
EWURA approves construction of petroleum facilities and issues operating licences.
Do I need an EIA for a filling station?
Yes. Petrol stations are among the projects that need environmental assessment through NEMC.
How big should a petrol station plot be?
Many stations need at least 1,500 to 3,000 m² so tankers can deliver and cars can queue without blocking the road. The final size comes from the layout and the regulator's requirements.
Can a petrol station be built in a residential area?
Distance and land use rules apply. Check zoning and regulator requirements before buying land.
What size tanks does a petrol station need?
It depends on expected sales and delivery frequency. Many stations have two to four tanks of 20,000 to 60,000 litres each for petrol and diesel.
How long does EWURA approval take?
Timing depends on how complete the application is and on other approvals such as the EIA. Allow several months and start early.
Can a petrol station have a car wash and shop?
Yes. Many stations add a shop, car wash or lube bay to earn more per customer. Plan space and drainage for them in the layout from the start.